How much cement, sand and coarse aggregate goes into your pour. Pick a standard grade or set your own ratio, and get cement in kilograms and bags, sand and aggregate by weight, and the water needed for the specified water-cement ratio.
1:2:4 is a volume ratio, and that is where the trouble starts
Nearly everyone reads it as weight. It is not. It means one volume of cement to two of sand to four of coarse aggregate — one bucket, two buckets, four buckets. Because cement is far denser than sand by volume, the same mix written out in kilograms looks nothing like 1:2:4, and a batch thrown together on a weighbridge will not come out right.
The second thing that catches people is the dry-volume factor. If you measure out 1 m³ of dry materials in the stated ratio and mix them, you do not get 1 m³ of concrete. You get noticeably less.
What goes into a cubic metre
| Grade | Ratio | Cement | Sand | Aggregate | Water | Typical use |
|---|---|---|---|---|---|---|
| M15 | 1 : 2 : 4 | 317 kg | 704 kg | 1,320 kg | 174 L | Levelling courses, footings, non-structural |
| M20 | 1 : 1.5 : 3 | 403 kg | 672 kg | 1,260 kg | 202 L | Residential slabs, beams and columns |
| M25 | 1 : 1 : 2 | 554 kg | 616 kg | 1,155 kg | 249 L | Structural members, heavy duty slabs |
Cement by weight; sand and aggregate by loose volume converted at 1,600 and 1,500 kg/m³. Water assumes a water-cement ratio of 0.55 for M15, 0.50 for M20 and 0.45 for M25.
Where 1.54 comes from
Coarse aggregate is mostly rock with gaps between the pieces. Sand fills those gaps. Cement paste fills the gaps in the sand. So the dry materials, measured loose before mixing, occupy roughly 54% more space than the concrete they eventually become — and 1.54 is the factor used to account for it.
dry volume = wet volume x 1.54 cement vol = dry volume x (cement parts / total parts) cement kg = cement vol x 1440 kg/m³ M20, 1 m³: dry = 1.54; total parts = 1 + 1.5 + 3 = 5.5 cement vol = 1.54 x 1/5.5 = 0.280 m³ -> 403 kg -> 9 bags of 50 kg
Four ways a hand-mixed batch misses its grade
- Damp sand bulks. Sand at around 5% moisture fluffs up and can occupy as much as 30% more volume than dry sand. Measure by volume and a wet batch is a leaner mix than you intended. Weigh it, or correct for bulking.
- Water gets added for workability. The water-cement ratio sets the strength. Making the mix easier to place by adding water is the single most common reason concrete fails to reach the grade it was specified at.
- Volume and weight get mixed up. See the top of this page. A gauge box filled differently — heaped, struck, compacted — also shifts the real ratio.
- The grade name is treated as a promise. M20 is a characteristic compressive strength of 20 N/mm² at 28 days under controlled conditions. A nominal 1:1.5:3 mix is a starting point. For structural work the mix should be designed and tested, not assumed.
The dry-volume method is standard nominal-mix practice. For designed mixes, follow the relevant national code — The Concrete Society publishes guidance for UK and European work, and the American Concrete Institute for US practice.
FAQ
What does the M in M20 stand for?
The characteristic compressive strength in N/mm² measured on a standard cube after 28 days of curing. M20 should reach 20 N/mm². The number is the grade, and higher grades carry more cement relative to aggregate — which is why M25 uses 554 kg of cement per cubic metre against M20's 403 kg.
Is the ratio by weight or by volume?
By volume, which is how the ratios are traditionally written — one bucket of cement to two of sand. Where accuracy matters, weigh it instead. Volume measurement is vulnerable to sand bulking and to how tightly the gauge box gets filled, and both shift the real ratio away from what you intended.
How much cement for 1 cubic metre of M20?
About 403 kg, which is 9 bags of 50 kg. Dry volume is 1.54 m³, the 1:1.5:3 ratio gives 5.5 total parts, so cement volume is 1.54 ÷ 5.5 = 0.28 m³, and at 1440 kg/m³ that is 403 kg.
Why is the dry volume 1.54 times the wet volume?
Because of voids. Sand fills the gaps between coarse aggregate particles, and cement paste fills the gaps in the sand. The dry materials measured loose occupy roughly 54% more space than the concrete they produce, so 1.54 is the correction factor.
How much water does M25 need?
Around 249 litres per cubic metre at a water-cement ratio of 0.45. Note the apparent contradiction: the ratio is lower than M20's 0.50, but the absolute water is higher, because M25 starts with more cement. Adjust downwards for moisture already sitting in your sand and aggregate.
Can I use a 1:2:4 mix for a house slab?
1:2:4 is M15 and is fine for levelling courses, footings and non-structural work. For a suspended slab or anything carrying structural load, M20 (1:1.5:3) is the usual minimum, and plenty of specifications call for M25. If a structural engineer has specified a grade, use that and not a nominal ratio.