How much concrete fills a round hole, once the post inside it is taken out. Enter the hole diameter, depth and how many you are digging, add the post size so it gets subtracted, and optionally add a bell-shaped footing at the bottom for frost country.
Post inside the hole (optional)
Set both to 0 if the hole is empty, or if you want the full hole volume.
Bell bottom footing (optional)
A wider base that resists frost heave. Leave at 0 for a straight hole. The bell height is part of the total depth, not added to it.
A post set 18 inches deep will lean
Not this winter. The winter after next. Water in the soil freezes, expands, and grips whatever is buried in it; the post comes up a fraction of an inch and does not go back down. Do that for a few seasons and a straight run of fencing develops a lean you cannot fix without digging the post out and starting again.
Which is why depth is the first number to settle, and the diameter is the second. Volume is a distant third — it is just what you get once the other two are decided.
How deep, and how wide
Depth answers to two rules at once, and you follow whichever asks for more:
- Below the frost line. Where the ground freezes, the bottom of the footing has to sit below that depth. Frost depth runs from effectively nothing along the Gulf Coast to 40–60 inches across the northern Plains and New England. In the UK the same idea is expressed as a minimum of about 600 mm, though exposed sites want more.
- A third of the post, plus 6 inches. For fence work the usual rule buries a third of the post and adds half a foot. A 6 ft fence wants at least a 2½ ft hole.
Deck footings are a different calculation entirely. They carry real load, so they are sized from the bearing capacity of the soil and the load above, and most inspectors want to see a specific diameter and depth on the plan rather than a rule of thumb.
Volume per foot of hole
These are raw hole volumes with nothing subtracted. Find your tube diameter, multiply by the depth, then take off the buried part of the post.
| Sonotube diameter | Volume per foot | 80 lb bags per foot | Volume at 3 ft deep |
|---|---|---|---|
| 6 in | 0.196 ft³ | 0.33 | 0.59 ft³ |
| 8 in | 0.349 ft³ | 0.58 | 1.05 ft³ |
| 10 in | 0.545 ft³ | 0.91 | 1.64 ft³ |
| 12 in | 0.785 ft³ | 1.31 | 2.36 ft³ |
| 16 in | 1.396 ft³ | 2.33 | 4.19 ft³ |
| 18 in | 1.767 ft³ | 2.95 | 5.30 ft³ |
| 24 in | 3.142 ft³ | 5.24 | 9.42 ft³ |
Bag figures assume a 0.60 ft³ yield per 80 lb bag. A 4×4 post occupies 0.111 ft² at nominal dimensions, so it removes about 0.33 ft³ from a 3 ft hole — roughly half a bag.
The bell bottom
A straight-sided plug works where the ground never freezes. In frost country the same plug can be gripped by the freezing soil and jacked slowly upward, post and all. Widening the base into a bell anchors it: the frost now has to lift the whole bell, and the soil sitting on top of the bell resists.
It used to be dug by hand with a shovel-shaped tool. Most people now get the same effect by using a wider sonotube for the full depth, or by dropping a precast footing pad in the bottom. That uses more concrete — it is the trade — but it is cheap insurance on anything you would mind seeing lean in five years.
Fill the hole, or just the bottom?
Both camps have a case. Filling the whole hole locks the post against sideways movement and traps water against the wood, which rots the base sooner. Concrete only the lower 6–12 inches and water drains away, but the post can work loose in sandy ground.
The version most builders actually do: concrete the bottom third to halfway, crown the top of the concrete slightly so water sheds off it, and backfill the rest with compacted gravel. If that is your plan, set the calculator to roughly half the hole depth.
If the holes you are pricing belong to a run of fencing rather than one post, the fence calculator takes the whole run at once, works out how many posts that needs, and adds the gate posts — which is where single-hole maths usually comes up short.
Depth and diameter guidance follows common practice set out by the American Concrete Institute and, for UK work, the The Concrete Society. Frost depth and soil bearing capacity are local — check both before you dig.
FAQ
How many bags per fence post?
An 8 in hole with a 4x4 post at 3 ft deep leaves about 0.71 cubic feet to fill, which is 1.2 bags of 80 lb — call it 2 bags per post once you round up. Ten posts is roughly 20 bags. Widening to a 10 in hole nearly doubles the concrete for very little extra holding power.
Do I have to concrete the full depth of the hole?
No, and there is a good argument for not doing it. Concreting the bottom third to halfway, crowning the top so water sheds away from the post, and backfilling the rest with compacted gravel drains better than a solid plug and holds almost as well in most soils. Set the calculator to about half the hole depth for that method.
What is the point of a bell-bottom footing?
It stops frost heave. A straight concrete plug can be gripped by freezing soil and jacked slowly out of the ground, post and all. Widening the base means the frost has to lift the entire bell, and the soil above the bell resists that. You use more concrete; you stop the post walking upward a little every winter.
Related calculators
Figures are estimates for planning. Local prices, bag yields and mix designs vary by supplier and region, so confirm with your ready-mix plant or builders merchant before ordering. Nothing you type is uploaded — every calculation runs in your browser.